Test Plan for MITICA GVS commissioning with CODAS and Interlock
Luchetta A.; Grando L.; Breda M.; Simionato P.; Moressa M.
pp. 1 - 11
Year:
2022
ISTP Authors: Luca Grando
Paola Simionato
Modesto Moressa
Keywords: NBTF, MITICA, CODAS, GVS, Gas Vacuum System, Interlock Systm
Research Activitie: PROJECT REPORTS
Related products
-
23rd Virtual IEEE Real Time Conference, , Virtual Conference , 1-5 August 2022 Year: 2022
The SPIDER Pulse Plant Configuration Environment
Cruz N.; Taliercio C.; Luchetta A.; Manduchi G.; Rigoni A.
-
23rd Virtual IEEE Real Time Conference, , Virtual Event , 1-5 August 2022 Year: 2022
Assessment of IEEE 1588-based timing system of the ITER Neutral Beam Test Facility
Trevisan L.; Luchetta A.; Manduchi G.; Taliercio C.; Rigoni A.; Barbato P.
-
pp. 1 - 8 Year: 2022 DOI: 10.1016/j.fusengdes.2021.112403
As-built Design Report of MITICA Control Room