Test Plan for MITICA GVS commissioning with CODAS and Interlock
Luchetta A.; Grando L.; Breda M.; Simionato P.; Moressa M.
pp. 1 - 11
Year:
2022
ISTP Authors: Luca Grando
Paola Simionato
Modesto Moressa
Keywords: NBTF, MITICA, CODAS, GVS, Gas Vacuum System, Interlock Systm
Research Activitie: PROJECT REPORTS
Related products
-
pp. 1 - 8 Year: 2022 DOI: 10.1016/j.fusengdes.2021.112403
As-built Design Report of MITICA Control Room
Carraro M.; Luchetta A.; Morandin M.; Zampiva E.
-
pp. 1 - 30 Year: 2021 DOI: 10.1007/s10462-021-10032-0
On-Site Acceptance Test Report and Certifications of the Rotating Platform
De Muri M.; Degli Agostini F.; Barzon A.; Fasolo D.
-
32nd Symposium on Fusion Technology - SOFT 2022, , Dubrovnik, Croatia / hybrid , 18-23 September 2022 Year: 2022
As built design of the control system of the ITER full-size beam source SPIDER in the Neutral Beam Tests Facility – A critical review
Luchetta A.; Taliercio C.; Cruz N.; Martini G.; Manduchi G.; Rigoni Garola A.; Trevisan L.; Paolucci F.; Labate C.V.